Installation guide of PVC spors flooring



Before Installation:
 
The Surface 
1. The construction surface must be clean, dry and no cracks.
2. the water content of concrete ground shall not exceed 2.5%, gypsum ground shall not exceed 0.5%.
3. Make sure it is flat (the error between 2 meters is not greater than 3 mm).
In addition, wood floors, tiles and other floor, whose flatness can meet the above requirements, can also be installed.
 
Flooring
It is important for the flooring to acclimatise for at least 24 hours, and the temperature should not be lower than 15°C. Unroll the flooring and cut it to size allowing an extra 5 cm to avoid being short of material at the end of the installation.
 
How to Install?
1. Mobile pavement: Make flooring together with a special single-side adhesive tape, no need to adhesive the ground, which can be
    movable.
2. Local fixed pavement: Use double-sided adhesive at the edge line of the flooring.
3. Fixed Pavement: Brush glue to the whole surface. It is better to use this way for basketball and tennis court. Otherwise, it will affect
    the rebound of the ball.
 

Heat welding method: The temperature of welding should not be less than 500°C, after fully cooled, remove the excess part of the welding rode. Whatever fixed pavement or not, welding rode can be used for each of them.